What are the details of the construction methods for valve wells?
Valve wells are open pipelines and open pipelines (such as water, oil, natural gas pipelines, etc.) of the valve in order to stop the need to open and close the local pipeline network operation or maintenance operations when a convenient kind of installation
Valve wells are open pipelines and open pipelines (such as water, oil, natural gas pipelines, etc.) of the valve in order to stop the need to open and close the local pipeline network operation or maintenance operations when a convenient kind of installation, in the open pipeline maintenance and liquidation play an important role.So what are the details of the construction method of the valve well?This issue of sealing valve well for you to make a move!
Valve well construction has more than one step, the details are as follows:
1, technical preparation
a engineering personnel familiar with, review the Shi T drawings and design clarification, familiar with the parts of each process construction methods and technical quality requirements, put forward a variety of construction plans to stop comparing.
b based on the existing manpower, equipment, materials based on the optimal combination of T period.Will be technologically advanced, easy to construct, economically rational construction organization plan declared to the contractor and supervision of a position for approval to guide the construction of the project.
cbased on the drawings and on-site construction program to provide a variety of materials order form and a variety of pre-embedded parts of the custom order.
d do material experiment and trial match work as the construction process of reliable basis.
e to the construction team to stop the detailed technical and quality requirements of the briefing.
2, material preparation
Bricklaying project for the brick for more than 75 number of mechanism brick size of 53 * 115 * 240 mm.No cracks, broken blocks or overcooked lumps form angular appearance flat, neat.Masonry before the submission of samples for approval by the supervisor before use.Concrete, reinforced concrete, reinforcing steel, cement, sand and gravel materials and doors and windows, a variety of veneer, rhinoceros surface waterproofing and thermal insulation materials should be in line with national and ministerial norms and by the supervision of the non early consent to be used.Materials before entering the field have cattle manufacturers to provide a certificate of conformity.
3, construction methods
Brick masonry
Set the elevation on the floor, with M 7.50 cement mortar or 10 fine stone concrete leveling so that the elevation of the bottom of each section of the brick wall to meet the design requirements.According to the set axis and the wall size marked on the drawings, use the ink line on the top of the foundation to pop up the wall axis and the wall width line, and separate the position line of the door grease ports.Brick masonry corners and intersections at the same time masonry or set into a hewer.Brick masonry to the regular elevation after the if you need to wait for the next process of construction, then sprinkler maintenance, and covered with moist straw bags.Brick masonry in the masonry after the completion of at least 5 days of maintenance, maintenance period to prevent rain or exposure to the sun.During the masonry process, use the method of three skins and one crane, five skins and one lean to eliminate masonry errors in the process of operation.Maintain the masonry for at least 5 days, prevent rain or sun exposure during the maintenance period.During the process of masonry, use the method of three skins and one crane, five skins and one leaning to eliminate masonry errors in the process of operation.Masonry wall mortar, in the masonry side of the masonry scraping, so as not to affect the layer of stucco.When the layer of brick masonry masonry finished immediately stop the wall clearing.Pay attention to the correct reservation of tie bars in the process of masonry.
Internal and external wall plastering
First check the wall leveling verticality by pulling the line to resolve the thickness of the thinnest plaster not less than 7 mm, and then in the upper corner of the wall to do a specification of the size of the ash cake 5 cm square thickness to the wall leveling vertical resolution and then based on the two ash cake with a pulling the line or a line hammer to hang a vertical line to do the lower corner of the wall two specification of the ash cake thickness to the vertical shall prevail.To be slightly dry after the ash cake in the upper and lower ash cake between the plaster about 5 cm wide mortar punch with a wooden board to scrape the thickness of divergence with the ash cake to be slightly dry after the bottom layer of plastering can be stopped.
Well cover
Prefabricated valve well cover plate concrete pouring with a poke ruler and pull a small line to check the plate thickness, elevation conditions top plate concrete pouring after the appearance of the scraping bar scraping plane layer with a wooden trowel rubbing flat to wait for the beginning of condensation when the concrete appearance need to stop the second rubbing surface and then the surface cover plastic film after the concrete demolding should be avoided after the end of the concrete pouring the Government to avoid sun exposure.After the concrete is poured, water should be poured within 12 hours to maintain the concrete for not less than 14 days, and only when the concrete strength reaches 1.2Mpa can people stop other construction work.
Quality assurance measures
Measurement and placement of the line to implement the placement of the line retesting system to ensure the accuracy of the placement of the line.
Concrete pouring strictly implement the concrete pouring application form system, and the concealed works must be accepted and signed before the next process can be stopped.
Set up a full-time quality inspector who can independently exercise the right to set up a part-time quality inspector at the same time.
Experimental personnel in accordance with the national standard requirements for raw materials sampling experiments in accordance with the request to retain the concrete test block.
The above is the valve well detailed construction method interpretation, hope that your understanding and operation of the construction staff to provide assistance.