06
Taiyuan Taikoo Heating Tunnel Project Officially Opened
It was reported that the Taikoo Heating Tunnel Project in Taiyuan City was officially opened. With the official opening of the Taikoo Heating Tunnel Project, the large-scale and extra-long distance it has created in China has also become a focus of attention in the industry.
Project Highlights
Energy saving and environmental protection
The total investment in the construction of the heating project is approximately RMB 4.8 billion, of which RMB 1.69 billion is invested in the tunnel.Upon completion of the project, a heating area of 50 million square meters can be realized in the near future and 76 million square meters in the long term, which will account for about half of the current total heating area of Taiyuan City.The project will produce huge environmental benefits and social benefits after construction.Annual savings of 931,000 tons of standard coal, electricity savings of 57 million degrees, water savings of 29.64 million tons, reducing carbon dioxide emissions of 2.44 million tons, reducing sulfur dioxide emissions of 3,798 tons, reducing nitrogen oxides emissions of 1,052 tons, reducing dust emissions of 2,104 tons, energy saving and environmental protection benefits are very significant.
Second, long distance
Taikoo supply line, will lay four 37.8 kilometers of heat pipes, each pipe diameter of 1.4 meters.Among them, the starting point of the tunnel is located in Wangfeng Township, Wanbailin District, Taiyuan City, Zhoujia Mountain, the end point is located in Dongshe Township, Dayan Village, and the need to cross the mountains, only the length of the tunnel is 15.17 kilometers, a total of three tunnels are set up, tunnel No. 1, 1,430 meters long, No. 2, 2,445 meters long, No. 3 tunnel length of 11,295 meters, a very long tunnel.
Third, the construction is difficult
Taikoo Heating Project was officially launched on March 1, 2014, and the tunnel project was fully completed on March 23 this year ahead of schedule.During the construction, the contractor solved many technical problems such as the construction of peripheral rock fracture zones, high-risk steep-slope inclined shaft lifting and transportation, and air supply and exhaust at the bottom of the large section inclined shaft.Due to the long distance of the heating pipeline transmission, Taiyuan, Gugiao there is a height difference, the diameter of the pipe up to 1.4 meters, the design of the heating pipeline, the technology is the first in the world.
▶ Dense steel ring dome to ensure tunnel safety
Taikoo Heating Project has a total of three tunnels, Tunnel 3 is the longest section of the tunnel in the Taikoo Heating Project, with a total length of 11,295 meters, and the opening of the tunnel project marks the completion of the entire Taikoo Heating Tunnel.
Driving into the tunnel, as the cave has just carried out a small gutter blasting, you can clearly see the smoke inside the cave.Into the tunnel, the light becomes dark, open car headlights, visibility is only 50 meters.Through the lights set on the right side of the cave wall, you can see an overview of the cave.
Overall, a cast tunnel hole has been molded, the surface is very neat, with the conditions for installation, the cave wall hanging ventilation, cables and other facilities, the tunnel floor is relatively flat, you can pass normally.Construction workers are welding a dense steel ring dome, this dense steel frame structure support alone in the 3rd section there are 43, it is these dense steel frame structure strongly support the entire tunnel, to ensure the safety of the tunnel.
▶ A number of technical processes of the project are of world-class level.
Inside the tunnel, every 100 meters, a groove appears in the tunnel wall, in which a dense mesh of steel bars is distributed.This is the bracket used to fix the heat supply pipe network. Due to the high terrain of Gujiao City, there is a 180-meter height difference with Taiyuan City, and it is necessary to fix the pipe network firmly on the bracket.Many of the designs and technologies used in the project are not referenced from conception to implementation, making them technically difficult.Currently, the design and technology of the main and secondary supports used in the project are of world-class level.
In the 10.6-meter-wide, 8-meter-high tunnel, a total of four heating lines are set up, respectively, on both sides, accounting for about 3 meters, leaving a 4-meter inspection channel in the middle.After the brackets are welded, 150 cm thick concrete will be injected into them to reinforce the brackets again, whereas in the normal case only 60 cm thick concrete is injected.
In addition, the project also encountered various challenges.For example, in the construction of peripheral rock fracture zone, in the process of tunnel opening, due to the crustal movement, the tunnel peripheral rock joints development, weathering is extremely serious, is a gravel-like mosaic structure, mechanical excavation after the collapse of a serious problem.There are 11 similar geological environments, which are also the most difficult part of the construction, mainly adopting the method of small conduit grouting, injecting cement slurry into the surrounding rock to make it solidify and then blasting, resulting in slower progress of the construction.
One of the tunnel's inclined shafts for ventilation is also of world-class level, which is the steepest inclined shaft in the country among similar projects.During the construction, the main difficulties encountered in the large section of the bottom of the inclined shaft to pick the top."In the construction of the inclined shaft bottom row, air supply channel circulation lane, the use of division excavation, erection of temporary support system, multi-step division excavation, and ultimately ensure the safety of large section pick top construction."
▶ Construction workers work overtime to ensure heating this winter
On-site construction personnel almost every day is a high-intensity work, taking into account the working environment, most of the construction workers here are about 40 years old strong labor force, relatively energetic.The busiest time of the work period, the site has about 100 people construction, using a process of a shift relay construction, such as blasting group blasting withdrew, by the mechanical group to enter the slag removal, framing group then enter, and finally the turn of the concrete class pouring, cycle turnover."Tunnel boring is a grueling project, the construction workers need to overcome dust pollution, accept the dark working environment, as well as high decibel noise.In addition, unlike ordinary workers, construction crews here work not in eight-hour shifts, but in frequent shifts."There will be four cycles, or four shifts in 24-hour shifts, when working in the deep shafts, and the construction crews will rest for five or six hours and work for two hours, which is an intermittent break.
From the beginning of construction to the tunnel through, 718 days around the clock.In order to make sure that the heat source of Gujiao Xingneng Power Plant can be used for heating this winter, the construction has never been interrupted, including New Year's Day, festivals and other holidays, and is not affected by any weather, and all the equipments are working at full capacity.
We are honored to have participated in the construction process of Taikoo Heating, and we are proud that we, "Tiandilongg", can contribute our little effort to the successful completion of the project.Our company has contracted the construction project of non-compensated electric preheating for DN1400 main line of Taikoo Heating Engineering. In order to ensure the construction progress, our company has transferred 12 sets of high-power electric heating equipments to the site, 12 sets of 1000kW original imported generators, and appointed 15 people for on-site management and construction to ensure the continuous operation of 6 DN1400 insulated pipelines at the same time for 24 hours, and we are proud of our high quality service and flexible construction methods.Our company with high quality service and flexible construction methods, to overcome the site construction difficulties, wide range of work, quality requirements, such as the reality of the problem, the completed preheating section all passed the acceptance, the A unit, the supervision unit, the construction unit unanimously recognized.
Uncompensated preheating installation is mainly applied to high temperature hot water pipelines with maximum operating temperature not exceeding 140ºC in urban heat pipe network.Because the uncompensated preheating installation adopts the technology of releasing stress in advance, thus reducing the number of fixed piers and compensators to a large extent, on the one hand, it reduces the construction and installation cost of the project, on the other hand, due to the reduction of the number of compensators, it improves the safety and reliability of the pipeline network, and reduces the operation and maintenance cost of the pipeline network significantly.Compared with the traditional uncompensated preheating installation, electric preheating installation is environmentally friendly and energy-saving, convenient construction, short construction period, can further reduce the project investment costs, is currently widely used in the international advanced insulation pipe uncompensated pre-stress installation.
Our company can meet the following preheating requirements:
-Maximum preheating pipe diameter DN1400mm
-Length of preheating pipe trench 1200 meters
-Simultaneous opening of 8 groups of pipe trenches for preheating
-Simultaneous preheating of insulated pipelines of different caliber
-Discontinuous pipelines can be preheated at the same time
-Replacement of damaged compensators in the old pipe network
-Preheating installations in urban centers where open trench conditions are not available
-Preheating time within 24 hours